RE: Proposed update of Milestones

On Tuesday, August 14, 2012 6:33 AM, Stefan Hakansson LK wrote:
> The chairs have drafted new milestones, and would like feedback on them. 
[...]
> Proposed milestones:
> FPWD: Q3 2011 (MS already passed, met in Q4 2011)
> LC: January 2013
> CR: March 2013
> PR: Q2 2013
> Rec: Q3 2012.
>
> Feedback appreciated!

LC->CR in two months assumes few comments and quick turnaround on the
disposition of comments and CfC to move to CR - might be fine but hard
to predict what external feedback might be received at this point.

Going from CR->PR in three months seems like a challenge (completing a
test suite, considering feedback generated by the tests, and presenting
implementation reports, etc.).

Cheers,

Adrian.