Re: IMSC 1.2 PR branch

   hi

   Sorry that I've not added post-PR from milestone calculator.
https://w3c.github.io/spec-releases/milestones/?pr=2020-06-11
says:

PR: 11-Jun-2020
Last day of AC review: 09-Jul-2020
Transition request to REC: 10-Jul-2020
REC: 16-Jul-2020 (really?)

   And one point, we need to consider of things for REC during PR period, like whether to have
a (press) release, preparation of introduction text (of spec) and/or? short summary for REC
announcement, etc. (as the same as previous REC release?)


   best,


On 2020/05/26 01:22, Pierre-Anthony Lemieux wrote:
> Hi Atsushi,
> 
> Thanks. I have updated the PR draft.
> 
> Can you confirm the end of the PR period? I suggested July 11.
> 
> Best,
> 
> -- Pierre
> 
> On Mon, May 25, 2020 at 9:03 AM Atsushi Shimono (W3C Team)
> <atsushi@w3.org> wrote:
>>
>>     hi Pierre,
>>
>>     Pushed PR as https://github.com/w3c/ttwg/pull/120, but how about to aim:
>>
>> CfC: 22-May-2020
>> End of CfC: 05-Jun-2020
>> Final PR document: 05-Jun-2020
>> Transition request: 05-Jun-2020 (1w for approval; W3C management call every Wed)
>> (Approval): 10-Jun-2020 (or earlier if possible???)
>> (Send publication request): 10-Jun-2020 (should be 1-2 days before publication)
>> PR publication: 11-Jun-2020
>>
>>
>>     best
>>
>>
>> On 2020/05/22 06:02, Pierre-Anthony Lemieux wrote:
>>> Good morning/evening,
>>>
>>> Per our call earlier today, I created the following pull request to
>>> track the IMSC 1.2 PR publication:
>>>
>>> https://github.com/w3c/imsc/pull/554
>>>
>>> The pull request is based on #552, which closes the last opened ticket
>>> against the IMSC 1.2 PR milestone.
>>>
>>> The dates are placeholders. Atsushi, can you suggest realistic dates,
>>> assuming the CfC starts on Friday CET?
>>>
>>> Best,
>>>
>>> -- Pierre
>>>
>>

Received on Tuesday, 26 May 2020 07:51:35 UTC