- From: Kirmse, Daniel <daniel.kirmse@sap.com>
- Date: Thu, 10 Jan 2002 12:32:22 +0100
- To: "Ietf-Dav-Versioning (E-mail)" <ietf-dav-versioning@w3.org>
Hi, a question dealing with activities: Suppose two workspaces A and B. Both of them are under baseline control on its own. Now suppose an activity C. Is there a server side mechanism defined in DeltaV that could prevent a client from checking out resources of WS A and B and including them by the way into activity C. Instead a client should be forced to checkout a resource of WS B into a different activity if activity C allready contains a checked out resource of workspace A. From reading the DeltaV I got no idea how to do this, propably it's not even there ... Thanks, Daniel
Received on Thursday, 10 January 2002 06:33:00 UTC