Schedule data from Crete, updated since f2f by the stuff in brackets, "[...]".
Last update: 2003-07-14.
activity/milestone | OpsGL | SpecGL | TestGL |
---|---|---|---|
current public WD | 5th | 4th | 2nd |
LC issues done | 100% | 90-95% [100% now] | n/a |
Revised text GL | 75% [95% now] | 60-70% [???] | -- |
Revised text ET | 0% [75% now] | 0% [???] | 0% (need ET before LC) |
Review revised text [R-to-C] | [in progress] | [pending] | -- |
Publish WD | [1st August] | ??? (Day3-am
minutes only refer to WG draft) |
WG-only, late July; 3rdPWD mid-Sept |
Draft DoC | [28th July] | 1st August ??? (minutes confusing) |
?? |
Send DoC to submitters, start negotiation |
[1st August] | ?? | |
CR Director call | [22nd August] | n/a | |
text for CR ready | [5th Sept] | Last Call (not CR) November. |
Most of the Crete f2f data is taken from the Day1-pm raw minutes.