Schedule data from Crete, updated since f2f by the stuff in brackets, "[...]".

Last update: 2003-07-14.

activity/milestone OpsGL SpecGL TestGL
current public WD 5th 4th 2nd
LC issues done 100% 90-95% [100% now] n/a
Revised text GL 75% [95% now] 60-70% [???] --
Revised text ET 0% [75% now] 0% [???] 0% (need ET before LC)
Review revised text [R-to-C] [in progress] [pending] --
Publish WD [1st August] ??? (Day3-am minutes only
refer to WG draft)
WG-only, late July;
3rdPWD mid-Sept
Draft DoC [28th July] 1st August ???
(minutes confusing)
??
Send DoC to submitters,
start negotiation
[1st August] ??
CR Director call [22nd August] n/a
text for CR ready [5th Sept] Last Call (not CR) November.

Most of the Crete f2f data is taken from the Day1-pm raw minutes.